The Worthington City Council on Monday awarded a contract for the reconstruction of Shell Street from Lake Avenue to Ninth Avenue.
The contract was given to Ideal Landscaping LLC in the amount of $387,132.50. The engineer’s estimate for the project was $475,380, meaning that the accepted bid was about 19% less than the cost that had been estimated.
Also bidding on the contract were Henning Construction and Duininck Inc. A start date has yet to be set for the work, which is scheduled to be finished by Oct. 20.