City council tables vote on lease and operations agreement for new arena

Oct 27
3 min read

The Worthington City Council on Monday tabled a vote on the lease and operations agreement on the planned new Worthington Ice Arena.


Council members went ahead with the approval of the finance and construction agreement for the new arena, as well as a use agreement. Regarding the lease and operations agreement between the city and Worthington Independent School District 518, concern was expressed that the deal was unfair to the city,


Councilman Mike Kuhle noted that the city is putting forward $10 of the $16 million in construction costs, and yet is being saddled with operating costs that will result in significant losses. He said the agreement "is a slap in the face. To me, this is not a fair stipulation." He called for a renegotiation of the agreement between the city, school district and Worthington Hockey Association.


Councilman Chris Kielblock agreed with Kuhle, adding that one solution could be isolating various costs such as ice operations, custodian service, operations maintenance, equipment and others so that they be split on an annual basis by the city, school district and hockey Association. He added that he had hoped a discussion about this type of cost-sharing would have taken place before now.


"If this isn’t addressed now, when will it be?" Kielblock asked Monday.


Councilwoman Amy Ernst stated that expenses such as capital maintenance and major building system replacements would be incurred by the landlord — which is the school district — and may ultimately offset what the city is paying, though not in a year. 


Councilwoman Amy Woitalewicz noted costs involving the parking lot, snow removal and lawn maintenance would be the district's, and the ice time rates negotiated on a yearly basis. Council member Dennis Weber agreed with the sentiment that the school district and hockey association share in operating costs.


Work will be able to continue moving forward on the arena, but the city will now try to gather additional information on how the lease and operations agreement could be changed. City Administrator Steve Robinson said there are no levy funds associated with the building of the new arena.


**


Also Monday, the council received reports and ordered a hearing on the East Flower Lane Extension Phase 2 project.


The council was required by state statute to order the improvement hearing to proceed with the assessment project. It approved reports on the proposed project of East Flower Lane from the existing East Flower Lane to First Avenue Southwest. The proposed improvements involve road base, grading, curb and gutter, sidewalks, concrete driveways, permanent pavement, water main, sanitary main, storm sewer main and sanitary services. Assessment will not commence until the full scope of work is completed.


The reports provide comprehensive information on the proposed improvements, including costs, funding, estimated assessment rates and the city’s share, along with related improvements. Council members scheduled hearings on the project to take place during the Nov. 23 council meeting.


Also Monday, a resolution authorizing execution of a Toward Zero Deaths Grant Agreement was approved by the council.


The Minnesota Department of Public Safety, Office of Traffic Safety, has initiated a Toward Zero Deaths Communities grant process, which runs from Oct. 1, 2026 through Sept. 30, 2027. The grant includes reimbursement funds for officers' overtime during operational waves, with a focus on traffic safety and impaired driving enforcement.


Adoption of the resolution allows Interim Director of Public Safety Nate Grimmius to execute the grant.